Once a completed net meter application packet is submitted to KEC, our staff will review the design specs of the proposed system and the capacity of our transformer to confirm it is sufficiently sized to accommodate this request. When our review is complete the member is notified they can proceed with installation. However, the system cannot be turned on or interconnected to our grid until we perform a final inspection. This is necessary to confirm the system is safely interconnected to our electric grid. Following a passed final inspection, members can begin generating power. KEC will also update the billing rate for the service address to provide credit for excess generation.